Question 1 of 137
Category: APCF – Project with a contract
What type of project is used in the billing rules lesson example?
Question 2 of 137
Which components are tracked in change management’s ‘Impact on planning’ section?
Please select the three correct options to score the point
Question 3 of 137
What triggers an adjustment request automatically when change management is enabled?
Question 4 of 137
Category: APCF – Linking multiple projects to one budget
How are budget lines identified in a linked budget shared across multiple projects?
Question 5 of 137
Category: APCF – Transactions committed costs and progress
What defines soft committed costs in purchase orders?
Question 6 of 137
Category: APCF – Transactions committed costs and progress
Which values appear in the reporting dataset?
Please select the 3 correct options to score the point.
Question 7 of 137
When publishing task planning, which indicators might signal over-budget activities?
Please select the two correct answers to score the point
Question 8 of 137
Steps to handle over-budget planning via adjustment request
Reorder
Update cost control budget
Move "Update cost control budget" down
Move "Update cost control budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Detect red icon on task planning
Move "Detect red icon on task planning" down
Move "Detect red icon on task planning" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create adjustment request
Move "Create adjustment request" down
Move "Create adjustment request" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Submit for approval
Move "Submit for approval" down
Move "Submit for approval" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 9 of 137
Category: APCF – Transactions committed costs and progress
Steps for posting and reflecting hours in project control
Reorder
Confirm dataset and update reporting
Move "Confirm dataset and update reporting" down
Move "Confirm dataset and update reporting" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Review actual costs and completion %
Move "Review actual costs and completion %" down
Move "Review actual costs and completion %" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Generate progress and estimate dataset
Move "Generate progress and estimate dataset" down
Move "Generate progress and estimate dataset" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Post hours through hour journal
Move "Post hours through hour journal" down
Move "Post hours through hour journal" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 10 of 137
Category: APCF – Introduction and agenda
Match topics to their training section
How to define costs and revenues on a project
Introduction of CPI and SPI
Collect budget vs actual data over time
Compare planned vs real effort and milestones
Budget creation
Correct
Incorrect
Correct answer
Earned value management
Correct
Incorrect
Correct answer
Progress snapshots
Correct
Incorrect
Correct answer
Change management
Correct
Incorrect
Correct answer
Question 11 of 137
Category: APCF – Cost Breakdown Structure templates
Which values can be automatically added when generating budget lines?
Please select the three correct options to score the point
Question 12 of 137
Category: APCF – Project with a contract
Match project planning elements to their function
Triggers project start billing
Requires hours and items
Enables linking of budget codes
Defines revenue by milestone
Kickoff milestone
Correct
Incorrect
Correct answer
Engineering task
Correct
Incorrect
Correct answer
CBS template
Correct
Incorrect
Correct answer
Billing rule
Correct
Incorrect
Correct answer
Question 13 of 137
Category: APCF – Deviations in PE data set and adjustment requests
Map variance types to their cause
Change in completion percentage
Update to remaining estimate
No change – incorrect configuration
Workflow disabled or skipped
Variance due to progress% drop
Correct
Incorrect
Correct answer
Variance from new ETC
Correct
Incorrect
Correct answer
Unchanged budget variance
Correct
Incorrect
Correct answer
Variance recorded with no approval
Correct
Incorrect
Correct answer
Question 14 of 137
Category: APCF – Introduction and agenda
Typical training flow presented in the introduction
Reorder
Create a project and budget
Move "Create a project and budget" down
Move "Create a project and budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Review reporting data and apply adjustments
Move "Review reporting data and apply adjustments" down
Move "Review reporting data and apply adjustments" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Link WBS to CBS
Move "Link WBS to CBS" down
Move "Link WBS to CBS" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create progress & estimate dataset
Move "Create progress & estimate dataset" down
Move "Create progress & estimate dataset" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 15 of 137
Category: APCF – Cost Breakdown Structure templates
What is the correct order for setting up a cost control budget?
Reorder
Select WBS
Move "Select WBS" down
Move "Select WBS" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create project
Move "Create project" down
Move "Create project" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Lock budget
Move "Lock budget" down
Move "Lock budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Generate budget
Move "Generate budget" down
Move "Generate budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 16 of 137
Category: APCF – Introduction and agenda
Map reporting tools to their usage
Shows KPI charts over periods
Basis for actual reporting data
Locks and activates project budget
Standardizes financial tracking
Reporting overview
Correct
Incorrect
Correct answer
Progress & estimate dataset
Correct
Incorrect
Correct answer
Budget version approval
Correct
Incorrect
Correct answer
CBS template linking
Correct
Incorrect
Correct answer
Question 17 of 137
Category: APCF – Deviations in PE data set and adjustment requests
Which adjustment request type is typically used for variance handling?
Question 18 of 137
Category: APCF – Configuration
What are valid options for distributing item and expense costs over time?
Please select the three correct options to score the point
Question 19 of 137
Category: APCF – Progress and estimate data set
Match system behavior with reservation status
Reduces non-committed cost
Increases non-committed cost
Has no impact on budget values
Persists across reporting refresh
Reservation added
Correct
Incorrect
Correct answer
Reservation deleted
Correct
Incorrect
Correct answer
Reservation inactive
Correct
Incorrect
Correct answer
Reservation saved
Correct
Incorrect
Correct answer
Question 20 of 137
Category: APCF – Cost Breakdown Structure templates
Why is the period code important in cost control budgeting?
Question 21 of 137
Category: APCF – Progress and estimate data set
Map dataset elements to their descriptions
What has been posted to the project
Confirmed receipts but not yet consumed
Planned value × % completion
Remaining cost based on performance
Actual cost
Correct
Incorrect
Correct answer
Hard committed cost
Correct
Incorrect
Correct answer
Earned value
Correct
Incorrect
Correct answer
Estimate to complete
Correct
Incorrect
Correct answer
Question 22 of 137
Category: APCF – Reporting data
Steps to generate and use reporting data
Reorder
Access reporting module from project
Move "Access reporting module from project" down
Move "Access reporting module from project" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Analyze values, KPIs, and trends
Move "Analyze values, KPIs, and trends" down
Move "Analyze values, KPIs, and trends" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create and confirm a progress and estimate dataset
Move "Create and confirm a progress and estimate dataset" down
Move "Create and confirm a progress and estimate dataset" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Select confirmed dataset
Move "Select confirmed dataset" down
Move "Select confirmed dataset" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 23 of 137
Category: APCF – Introduction and agenda
Sequence of core financial tracking concepts introduced
Reorder
Earned value management
Move "Earned value management" down
Move "Earned value management" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Progress tracking via snapshots
Move "Progress tracking via snapshots" down
Move "Progress tracking via snapshots" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Revenue recognition adjustment
Move "Revenue recognition adjustment" down
Move "Revenue recognition adjustment" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Reporting via drill-down
Move "Reporting via drill-down" down
Move "Reporting via drill-down" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 24 of 137
Category: APCF – Earned value management
Steps to evaluate project performance using EVM
Reorder
Track actual costs
Move "Track actual costs" down
Move "Track actual costs" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Calculate planned value
Move "Calculate planned value" down
Move "Calculate planned value" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Calculate EV, CPI, and SPI
Move "Calculate EV, CPI, and SPI" down
Move "Calculate EV, CPI, and SPI" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Determine percentage of completion
Move "Determine percentage of completion" down
Move "Determine percentage of completion" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 25 of 137
Category: APCF – Introduction and agenda
Which tools are emphasized in project progress and budgeting?
Question 26 of 137
Category: APCF – Set progress Tracking level in CBS
Which option allows tracking progress on a summary CBS level?
Question 27 of 137
Match change types to approval needs
Needs approval via adjustment request
Is only automatically tracked with change management
Can be handled with standard adjustment request
Needs multi-project workflow
Change in effort
Correct
Incorrect
Correct answer
Milestone delay
Correct
Incorrect
Correct answer
Budget increase only
Correct
Incorrect
Correct answer
Multi-project effort shift
Correct
Incorrect
Correct answer
Question 28 of 137
Category: APCF – Deviations in PE data set and adjustment requests
Which values can cause a variance in a progress and estimate dataset?
Please select the two correct options to score the point
Question 29 of 137
Category: APCF – Transactions committed costs and progress
What can be set within cost control parameters?
Please select the 3 correct options to score the point.
Question 30 of 137
Category: APCF – Reporting data
Which values are visible in the reporting data grid?
Please select the three correct options to score the point
Question 31 of 137
Category: APCF – Linking multiple projects to one budget
Steps to link a project to an existing budget
Reorder
Set up billing rule
Move "Set up billing rule" down
Move "Set up billing rule" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Link new project to existing budget
Move "Link new project to existing budget" down
Move "Link new project to existing budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create new version of main project budget
Move "Create new version of main project budget" down
Move "Create new version of main project budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create new project and planning
Move "Create new project and planning" down
Move "Create new project and planning" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 32 of 137
Category: APCF – Cost Breakdown Structure templates
Which settings or elements appear in a cost control budget?
Please select the three correct options to score the point
Question 33 of 137
Category: APCF – Transactions committed costs and progress
Which element determines the cost of posted hours in a project?
Question 34 of 137
Match the adjustment request types to their function
Move budget between CBS codes
Increase budget
Decrease budget
Move budget with conditions
Mutation
Correct
Incorrect
Correct answer
Variation order
Correct
Incorrect
Correct answer
Reduction order
Correct
Incorrect
Correct answer
Transfer order
Correct
Incorrect
Correct answer
Question 35 of 137
Category: APCF – Progress and estimate data set
Steps to create a progress and estimate dataset
Reorder
Confirm dataset for reporting use
Move "Confirm dataset for reporting use" down
Move "Confirm dataset for reporting use" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create a new dataset and define transaction date
Move "Create a new dataset and define transaction date" down
Move "Create a new dataset and define transaction date" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Review CBS, categories and values
Move "Review CBS, categories and values" down
Move "Review CBS, categories and values" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Open the project cost control ribbon
Move "Open the project cost control ribbon" down
Move "Open the project cost control ribbon" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 36 of 137
Category: APCF – Transactions committed costs and progress
Which steps lead to actual costs in the PO lifecycle?
Please select the 3 correct options to score the point.
Question 37 of 137
Category: APCF – Solution introduction
Match solution components to function
Defines standardized budget hierarchy
Captures actuals vs budget over time
Displays KPIs like CPI and SPI
Used to revise budgets post-planning
CBS template
Correct
Incorrect
Correct answer
Progress and estimate dataset
Correct
Incorrect
Correct answer
Reporting data
Correct
Incorrect
Correct answer
Adjustment request
Correct
Incorrect
Correct answer
Question 38 of 137
Category: APCF – Transactions committed costs and progress
When is a cost considered actual in the PO lifecycle?
Question 39 of 137
Category: APCF – Progress and estimate data set
Which type of data set must be confirmed before it can be used in reporting?
Question 40 of 137
Category: APCF – Transactions committed costs and progress
How does the system classify cost states?
Reorder
Actual
Move "Actual" down
Move "Actual" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Soft committed
Move "Soft committed" down
Move "Soft committed" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Closed
Move "Closed" down
Move "Closed" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Hard committed
Move "Hard committed" down
Move "Hard committed" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 41 of 137
Which additional project elements does change management track beyond budget changes?
Question 42 of 137
Which elements can differ between projects in a multi-project adjustment request?
Please select the two correct answers to score the point
Question 43 of 137
Category: APCF – Deviations in PE data set and adjustment requests
What must be configured to create adjustment requests automatically from P&E variances?
Please select the two correct options to score the point
Question 44 of 137
Category: APCF – Introduction and agenda
Which elements are part of the solution’s agenda as presented in the training?
Question 45 of 137
Category: APCF – Configuration
Match configuration features to their purpose
Used if no sales category found in budget wizard
Customize forecast logic per project category
Allows tracking of soft and hard commitments
Prevents posting on specific CBS activities
Fallback sales category
Correct
Incorrect
Correct answer
ETC method override
Correct
Incorrect
Correct answer
Enable committed costs
Correct
Incorrect
Correct answer
Locked CBS code
Correct
Incorrect
Correct answer
Question 46 of 137
Category: APCF – Set progress Tracking level in CBS
Why would a group budget line be created?
Please select the three correct options to score the point
Question 47 of 137
What is created when changes are published across multiple projects with change management enabled?
Question 48 of 137
Category: APCF – Configuration
Which parameter enables change management per project stage?
Question 49 of 137
Category: APCF – Linking multiple projects to one budget
What are benefits of linking multiple projects to one budget?
Please select the three correct options to score the point
Question 50 of 137
Category: APCF – Reporting data
What is the purpose of the reporting data in project controlling?
Question 51 of 137
Category: APCF – Configuration
Map general settings to their expected outcome
Enables column customization in estimates
Allows reporting data to be updated automatically
Controls data entry depending on project status
Applies distribution by project planning duration
Use simplified data set
Correct
Incorrect
Correct answer
Auto-confirm progress data sets
Correct
Incorrect
Correct answer
Lock budget per stage
Correct
Incorrect
Correct answer
Distribute cost by WBS
Correct
Incorrect
Correct answer
Question 52 of 137
Workflow structure for multi-project adjustment requests
Reorder
Link to standard adjustment workflow
Move "Link to standard adjustment workflow" down
Move "Link to standard adjustment workflow" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Optionally add per-project approvals
Move "Optionally add per-project approvals" down
Move "Optionally add per-project approvals" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Define multi-project approval element
Move "Define multi-project approval element" down
Move "Define multi-project approval element" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Post changes to budget
Move "Post changes to budget" down
Move "Post changes to budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 53 of 137
Category: APCF – Project with a contract
Sequence of project setup based on training content
Reorder
Link CBS template
Move "Link CBS template" down
Move "Link CBS template" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Configure billing rules for milestones
Move "Configure billing rules for milestones" down
Move "Configure billing rules for milestones" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Build task planning and activities
Move "Build task planning and activities" down
Move "Build task planning and activities" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create project
Move "Create project" down
Move "Create project" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 54 of 137
Category: APCF – Progress and estimate data set
Steps to enable reservations in cost control settings
Reorder
Open cost control parameters
Move "Open cost control parameters" down
Move "Open cost control parameters" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Save settings and apply to project
Move "Save settings and apply to project" down
Move "Save settings and apply to project" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Navigate to committed cost section
Move "Navigate to committed cost section" down
Move "Navigate to committed cost section" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Enable manual budget reservation toggle
Move "Enable manual budget reservation toggle" down
Move "Enable manual budget reservation toggle" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 55 of 137
Category: APCF – Solution introduction
Link budgeting features to their configuration tool
Set in cost control parameters
Configured in budget form
Workflow-based activation
Set via billing rules
ETC method
Correct
Incorrect
Correct answer
Period split settings
Correct
Incorrect
Correct answer
Budget locking logic
Correct
Incorrect
Correct answer
Revenue milestone allocation
Correct
Incorrect
Correct answer
Question 56 of 137
Category: APCF – Project with a contract
What information must be added when creating a billing rule for a milestone?
Please select the three correct options to score the point
Question 57 of 137
Steps in multi-project change management publishing
Reorder
Submit for approval and post changes
Move "Submit for approval and post changes" down
Move "Submit for approval and post changes" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Publish with change management enabled
Move "Publish with change management enabled" down
Move "Publish with change management enabled" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Select projects and edit planning
Move "Select projects and edit planning" down
Move "Select projects and edit planning" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create multi-project adjustment request
Move "Create multi-project adjustment request" down
Move "Create multi-project adjustment request" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 58 of 137
Why might multiple approval levels be required for a multi-project adjustment request?
Question 59 of 137
Category: APCF – Transactions committed costs and progress
What are effects of editing progress % manually in the dataset?
Please select the two correct options to score the point
Question 60 of 137
Category: APCF – Progress and estimate data set
What types of progress calculations are available?
Select the three correct answers to score the point
Question 61 of 137
Category: APCF – Transactions committed costs and progress
Match dataset features to insights
Shows completion rate
Estimate to complete
Estimate at completion
See PO and transaction lines
Progress %
Correct
Incorrect
Correct answer
ETC
Correct
Incorrect
Correct answer
EAC
Correct
Incorrect
Correct answer
Drill-down
Correct
Incorrect
Correct answer
Question 62 of 137
Category: APCF – Transactions committed costs and progress
Match items to their committed state
Soft committed
Hard committed
Actual cost
Non-committed
PO Created
Correct
Incorrect
Correct answer
Received Items
Correct
Incorrect
Correct answer
Packing Slip
Correct
Incorrect
Correct answer
Transaction Unposted
Correct
Incorrect
Correct answer
Question 63 of 137
Category: APCF – Introduction and agenda
What core methodology does the solution implement for progress analysis?
Question 64 of 137
Steps triggered by publishing task planning with change management enabled
Reorder
Route through workflow approval
Move "Route through workflow approval" down
Move "Route through workflow approval" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Update cost control budget
Move "Update cost control budget" down
Move "Update cost control budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Auto-generate adjustment request
Move "Auto-generate adjustment request" down
Move "Auto-generate adjustment request" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Detect changes in planning
Move "Detect changes in planning" down
Move "Detect changes in planning" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 65 of 137
Steps to enable change management in Dynamics
Reorder
Activate change management toggle in cost control parameters
Move "Activate change management toggle in cost control parameters" down
Move "Activate change management toggle in cost control parameters" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Enable per project stage
Move "Enable per project stage" down
Move "Enable per project stage" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Define adjustment request types
Move "Define adjustment request types" down
Move "Define adjustment request types" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Set instant publish option if needed
Move "Set instant publish option if needed" down
Move "Set instant publish option if needed" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 66 of 137
Category: APCF – Linking multiple projects to one budget
Publishing process for linked budgets
Reorder
Submit for workflow approval
Move "Submit for workflow approval" down
Move "Submit for workflow approval" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Publish planning in each project
Move "Publish planning in each project" down
Move "Publish planning in each project" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create cost control budget per project
Move "Create cost control budget per project" down
Move "Create cost control budget per project" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Validate CBS mapping
Move "Validate CBS mapping" down
Move "Validate CBS mapping" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 67 of 137
Category: APCF – Earned value management
What is the formula for calculating Earned Value (EV)?
Question 68 of 137
What happens after submitting an adjustment request for approval?
Question 69 of 137
Typical sequence of creating a project adjustment request
Reorder
Submit to workflow
Move "Submit to workflow" down
Move "Submit to workflow" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Describe impact
Move "Describe impact" down
Move "Describe impact" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Enter budget lines and amounts
Move "Enter budget lines and amounts" down
Move "Enter budget lines and amounts" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Select adjustment request type
Move "Select adjustment request type" down
Move "Select adjustment request type" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 70 of 137
Category: APCF – Linking multiple projects to one budget
What must be done before linking a new project to an existing cost control budget?
Question 71 of 137
Category: APCF – Transactions committed costs and progress
What happens when hours are posted through an hour journal?
Question 72 of 137
Category: APCF – Linking multiple projects to one budget
Map budget states to required actions
Editable and ready for linking
Must be versioned before editing
Shares data across projects
In workflow queue for approval
Draft
Correct
Incorrect
Correct answer
Approved
Correct
Incorrect
Correct answer
Linked
Correct
Incorrect
Correct answer
Submitted
Correct
Incorrect
Correct answer
Question 73 of 137
Category: APCF – Introduction and agenda
What does the extension project controlling solution primarily help with?
Question 74 of 137
Category: APCF – Progress and estimate data set
Map reservation components to their meaning
Budget value set aside for specific needs
Budget not yet reserved or committed
Indicates when cost is expected to occur
Project expense category used for tracking
Reserved amount
Correct
Incorrect
Correct answer
Non-committed cost
Correct
Incorrect
Correct answer
Reservation date
Correct
Incorrect
Correct answer
Cost group
Correct
Incorrect
Correct answer
Question 75 of 137
Which of the following are required components of an adjustment request?
Please select all three correct answers to score the point
Question 76 of 137
Sequence of events when publishing changes with change management enabled
Reorder
Auto-generate adjustment request
Move "Auto-generate adjustment request" down
Move "Auto-generate adjustment request" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Detect milestone or effort changes
Move "Detect milestone or effort changes" down
Move "Detect milestone or effort changes" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Submit request to workflow
Move "Submit request to workflow" down
Move "Submit request to workflow" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Update project budget and planning
Move "Update project budget and planning" down
Move "Update project budget and planning" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 77 of 137
Category: APCF – Transactions committed costs and progress
ETC/EAC impact sequence after hour posting
Reorder
Recalculate progress % from hours
Move "Recalculate progress % from hours" down
Move "Recalculate progress % from hours" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Post actual hours
Move "Post actual hours" down
Move "Post actual hours" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Calculate EAC using ETC and actual cost
Move "Calculate EAC using ETC and actual cost" down
Move "Calculate EAC using ETC and actual cost" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Determine ETC based on new progress
Move "Determine ETC based on new progress" down
Move "Determine ETC based on new progress" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 78 of 137
Category: APCF – Transactions committed costs and progress
Which cost states are discussed in the configuration?
Please select the 3 correct options to score the point.
Question 79 of 137
Which of the following features is unique to change management compared to standard adjustment requests?
Question 80 of 137
Category: APCF – Deviations in PE data set and adjustment requests
What triggers automatic creation of an adjustment request from a progress and estimate dataset?
Question 81 of 137
Category: APCF – Solution introduction
Basic implementation flow for project controlling
Reorder
Create project and task planning
Move "Create project and task planning" down
Move "Create project and task planning" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Track progress and reporting through snapshots
Move "Track progress and reporting through snapshots" down
Move "Track progress and reporting through snapshots" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Generate and approve cost control budget
Move "Generate and approve cost control budget" down
Move "Generate and approve cost control budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Link WBS to CBS structure
Move "Link WBS to CBS structure" down
Move "Link WBS to CBS structure" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 82 of 137
Which conditions are required for change management to be active?
Please select all three correct answers to score the point
Question 83 of 137
Category: APCF – Reporting data
Version comparison process in reporting data
Reorder
Approve the new version of the budget
Move "Approve the new version of the budget" down
Move "Approve the new version of the budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Analyze changes across CBS codes
Move "Analyze changes across CBS codes" down
Move "Analyze changes across CBS codes" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create new version of project budget
Move "Create new version of project budget" down
Move "Create new version of project budget" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Select baseline version for comparison
Move "Select baseline version for comparison" down
Move "Select baseline version for comparison" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 84 of 137
Category: APCF – Transactions committed costs and progress
Match each cost term with its meaning
PO created, not received
Items received, not consumed
Items consumed (packing slip)
No PO or action yet
Soft Committed
Correct
Incorrect
Correct answer
Hard Committed
Correct
Incorrect
Correct answer
Actual
Correct
Incorrect
Correct answer
Non-Committed
Correct
Incorrect
Correct answer
Question 85 of 137
Category: APCF – Configuration
Which features are configurable within the cost control parameters?
Please select the three correct options to score the point
Question 86 of 137
Category: APCF – Progress and estimate data set
What is the purpose of the progress and estimate data set?
Question 87 of 137
Category: APCF – Transactions committed costs and progress
What can affect the calculated progress percentage in a dataset?
Please select the three correct options to score the point
Question 88 of 137
Category: APCF – Reporting data
Which dataset serves as the foundation for the reporting data?
Question 89 of 137
Category: APCF – Cost Breakdown Structure templates
Match the term with its role in budgeting
Defines time intervals for planning
Represents activities and tasks
Links cost elements to structure
Represents cost or revenue item
Period Code
Correct
Incorrect
Correct answer
WBS
Correct
Incorrect
Correct answer
CBS Code
Correct
Incorrect
Correct answer
Budget Line
Correct
Incorrect
Correct answer
Question 90 of 137
Category: APCF – Progress and estimate data set
Steps to create a reservation in the dataset
Reorder
Click on 'Create reservation'
Move "Click on 'Create reservation'" down
Move "Click on 'Create reservation'" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Enter amount and date, then save
Move "Enter amount and date, then save" down
Move "Enter amount and date, then save" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Select a dataset line
Move "Select a dataset line" down
Move "Select a dataset line" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Open unconfirmed progress and estimate dataset
Move "Open unconfirmed progress and estimate dataset" down
Move "Open unconfirmed progress and estimate dataset" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 91 of 137
Category: APCF – Earned value management
What insights does Earned Value Management (EVM) provide?
Please select the three correct options to score the point
Question 92 of 137
Category: APCF – Reporting data
What can users do from within the reporting data view?
Please select the three correct options to score the point
Question 93 of 137
Category: APCF – Progress and estimate data set
What are the characteristics of reservations in a progress and estimate dataset?
Select the three correct answers to score the point
Question 94 of 137
Category: APCF – Solution introduction
What are key capabilities added by the Axtension project controlling solution?
Please select the three correct options to score the point
Question 95 of 137
Category: APCF – Configuration
What is the recommended budgeting method when using the project controlling solution?
Question 96 of 137
What does an adjustment request allow you to do in project planning?
Question 97 of 137
Category: APCF – Progress and estimate data set
What configuration enables manual reservations in the dataset?
Question 98 of 137
Category: APCF – Project with a contract
Which elements are part of the example project task planning structure?
Please select the three correct options to score the point
Question 99 of 137
Category: APCF – Project with a contract
Steps to set up billing rules on a project
Reorder
Link CBS template to project
Move "Link CBS template to project" down
Move "Link CBS template to project" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Assign milestone, description, and value
Move "Assign milestone, description, and value" down
Move "Assign milestone, description, and value" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Open contract and add billing rule
Move "Open contract and add billing rule" down
Move "Open contract and add billing rule" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create project and task planning
Move "Create project and task planning" down
Move "Create project and task planning" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 100 of 137
Category: APCF – Solution introduction
What can be configured within the cost control budget module?
Please select the three correct options to score the point
Question 101 of 137
Category: APCF – Cost Breakdown Structure templates
Match each feature to what it supports
Forecasts remaining costs
Generates income lines
Groups budget lines
Approves and locks the budget
ETC Method
Correct
Incorrect
Correct answer
Revenue Rule
Correct
Incorrect
Correct answer
Cost Group
Correct
Incorrect
Correct answer
Workflow
Correct
Incorrect
Correct answer
Question 102 of 137
Category: APCF – Transactions committed costs and progress
Map project metrics to calculation inputs
Posted hours x cost rate
Based on posted hours or manual input
Based on budget and earned value
Actual cost plus ETC
Actual cost
Correct
Incorrect
Correct answer
Progress %
Correct
Incorrect
Correct answer
ETC
Correct
Incorrect
Correct answer
EAC
Correct
Incorrect
Correct answer
Question 103 of 137
Category: APCF – Set progress Tracking level in CBS
What happens when progress is tracked on the lowest CBS level?
Please select the two correct options to score the point
Question 104 of 137
Category: APCF – Set progress Tracking level in CBS
What is the default level for tracking progress in the CBS structure?
Question 105 of 137
Category: APCF – Transactions committed costs and progress
Match the description to the correct component
Posts actual hours to CBS activity
Is based on actual to progress, based on the WBS or changed manually
Progress & estimate datasets
Links activity to budget line
Hour journal
Correct
Incorrect
Correct answer
Progress%
Correct
Incorrect
Correct answer
Create snapshot of budget and actuals
Correct
Incorrect
Correct answer
CBS code
Correct
Incorrect
Correct answer
Question 106 of 137
Compare features of Adjustment Request vs. Change Management
Adjustment Request only
Change Management only
Both
Change Management only
Free-text impact fields
Correct
Incorrect
Correct answer
Tracks milestone shifts
Correct
Incorrect
Correct answer
Supports budget updates
Correct
Incorrect
Correct answer
Automatic adjustment request creation
Correct
Incorrect
Correct answer
Question 107 of 137
Category: APCF – Deviations in PE data set and adjustment requests
Match process steps to progress and estimate tracking
Triggers recalculated variance
Triggers auto adjustment request
Routes to approval workflow
Updates cost control budget
Change percentage
Correct
Incorrect
Correct answer
Confirm dataset
Correct
Incorrect
Correct answer
Submit adjustment
Correct
Incorrect
Correct answer
Approve request
Correct
Incorrect
Correct answer
Question 108 of 137
Map publishing scenarios to system behavior
Auto-creates adjustment request
Planning becomes live immediately
Budget not updated
User must create adjustment manually
Publish with change mgmt enabled
Correct
Incorrect
Correct answer
Publish with instant publish enabled
Correct
Incorrect
Correct answer
Publish without workflow approval
Correct
Incorrect
Correct answer
Manual publish without change mgmt
Correct
Incorrect
Correct answer
Question 109 of 137
Category: APCF – Linking multiple projects to one budget
Link setup elements and their purpose
Adds revenue to linked project
Ensures tasks align with budget codes
Connects project to shared budget
Identifies source project
Billing rule
Correct
Incorrect
Correct answer
Link WBS to CBS
Correct
Incorrect
Correct answer
Existing budget option
Correct
Incorrect
Correct answer
Project ID in budget line
Correct
Incorrect
Correct answer
Question 110 of 137
Category: APCF – Deviations in PE data set and adjustment requests
Steps from variance to approved budget adjustment
Reorder
Confirm progress and estimate dataset
Move "Confirm progress and estimate dataset" down
Move "Confirm progress and estimate dataset" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Generate adjustment request
Move "Generate adjustment request" down
Move "Generate adjustment request" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Identify variance in P&E dataset
Move "Identify variance in P&E dataset" down
Move "Identify variance in P&E dataset" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Submit for approval
Move "Submit for approval" down
Move "Submit for approval" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 111 of 137
Category: APCF – Reporting data
Map KPI values to their meaning
Cost-efficient performance
Lagging behind schedule
Over budget
Ahead of planned timeline
CPI > 1
Correct
Incorrect
Correct answer
SPI < 1
Correct
Incorrect
Correct answer
CPI < 1
Correct
Incorrect
Correct answer
SPI > 1
Correct
Incorrect
Correct answer
Question 112 of 137
Category: APCF – Reporting data
Match reporting features to functionality
View details like invoices and cost lines
Graphical display of project development
Analyze changes between budgets
Distributes costs and revenue over time
Drill-down
Correct
Incorrect
Correct answer
Reporting overview
Correct
Incorrect
Correct answer
Version comparison
Correct
Incorrect
Correct answer
Period split data
Correct
Incorrect
Correct answer
Question 113 of 137
Category: APCF – Progress and estimate data set
Which features can be configured for progress and estimate datasets?
Select the three correct answers to score the point
Question 114 of 137
Category: APCF – Progress and estimate data set
What is the purpose of a reservation in a progress and estimate dataset?
Question 115 of 137
In what ways does change management enhance project control compared to adjustment requests?
Please select the three correct options to score the point
Question 116 of 137
Category: APCF – Project with a contract
What must be done to link activities to a CBS code in the project?
Question 117 of 137
What does change management automatically generate when changes are published in task planning?
Question 118 of 137
Category: APCF – Set progress Tracking level in CBS
Steps to enable progress tracking at summary level
Reorder
Open cost breakdown structure template
Move "Open cost breakdown structure template" down
Move "Open cost breakdown structure template" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create group budget line
Move "Create group budget line" down
Move "Create group budget line" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Uncheck 'Track progress on descendants'
Move "Uncheck 'Track progress on descendants'" down
Move "Uncheck 'Track progress on descendants'" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Add quantity to summary CBS code
Move "Add quantity to summary CBS code" down
Move "Add quantity to summary CBS code" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 119 of 137
Category: APCF – Earned value management
Which KPI indicates if a project is staying within budget?
Question 120 of 137
What are key features of the multi-project adjustment approval workflow?
Please select the two correct answers to score the point
Question 121 of 137
Category: APCF – Earned value management
Match EVM metrics with their meaning
Cost efficiency of the project
Schedule efficiency of the project
Remaining cost to finish project
Forecast of total project cost
CPI
Correct
Incorrect
Correct answer
SPI
Correct
Incorrect
Correct answer
ETC
Correct
Incorrect
Correct answer
EAC
Correct
Incorrect
Correct answer
Question 122 of 137
Category: APCF – Progress and estimate data set
Which values are tracked when a reservation is created?
Select the three correct answers to score the point
Question 123 of 137
Category: APCF – Solution introduction
Which element links project tasks to budget structure in the solution?
Question 124 of 137
Category: APCF – Cost Breakdown Structure templates
How does period splitting typically proceed?
Reorder
Define period code
Move "Define period code" down
Move "Define period code" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Calculate periods
Move "Calculate periods" down
Move "Calculate periods" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Apply adjustments
Move "Apply adjustments" down
Move "Apply adjustments" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Distribute costs
Move "Distribute costs" down
Move "Distribute costs" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 125 of 137
Category: APCF – Transactions committed costs and progress
What triggers costs related to purchase orders becoming hard committed?
Question 126 of 137
Match system behavior with project budget stages
Budget overrun detected
Budget within limits
Task planning under edit
Budget is active
Red icon shown
Correct
Incorrect
Correct answer
Green icon shown
Correct
Incorrect
Correct answer
Draft version created
Correct
Incorrect
Correct answer
Workflow approved
Correct
Incorrect
Correct answer
Question 127 of 137
Category: APCF – Earned value management
Match budget behavior with period performance
Project is under budget
Project is behind schedule
Project is over budget
Project is ahead of schedule
CPI > 1
Correct
Incorrect
Correct answer
SPI < 1
Correct
Incorrect
Correct answer
CPI < 1
Correct
Incorrect
Correct answer
SPI > 1
Correct
Incorrect
Correct answer
Question 128 of 137
Category: APCF – Cost Breakdown Structure templates
What is one advantage of using the project plan instead of a CBS template when creating a budget?
Question 129 of 137
What happens when ‘Instant Publish’ is enabled during change management?
Please select both correct answers to score the point
Question 130 of 137
Category: APCF – Project with a contract
Match billing rule setup fields to purpose
Specifies event to bill against
Gives context for invoice entry
Determines revenue amount
Pulled from linked task timeline
Milestone
Correct
Incorrect
Correct answer
Description
Correct
Incorrect
Correct answer
Value
Correct
Incorrect
Correct answer
Date
Correct
Incorrect
Correct answer
Question 131 of 137
Category: APCF – Transactions committed costs and progress
What is the sequence for cost state transition?
Reorder
Product receipt
Move "Product receipt" down
Move "Product receipt" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Packing slip
Move "Packing slip" down
Move "Packing slip" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Actuals recorded
Move "Actuals recorded" down
Move "Actuals recorded" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
PO created
Move "PO created" down
Move "PO created" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 132 of 137
Category: APCF – Linking multiple projects to one budget
Which actions are required when linking a project to an existing budget?
Please select the three correct options to score the point
Question 133 of 137
Category: APCF – Solution introduction
Budget to reporting flow in project controlling
Reorder
Track costs via P&E snapshots
Move "Track costs via P&E snapshots" down
Move "Track costs via P&E snapshots" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Review data in reporting view
Move "Review data in reporting view" down
Move "Review data in reporting view" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Create budget with WBS estimates
Move "Create budget with WBS estimates" down
Move "Create budget with WBS estimates" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Reorder
Split budget over time using period codes
Move "Split budget over time using period codes" down
Move "Split budget over time using period codes" up
answer is
Correct
is the
Correct Answer
answer is
Incorrect
Question 134 of 137
Map workflow elements to their purpose
Approves changes across all projects
Approves individual project changes
Workflow for approval of adjustment requests
Budget is updated according to adjustment request
Multi-project adjustment approval
Correct
Incorrect
Correct answer
Per-project approval
Correct
Incorrect
Correct answer
Adjustment request approval workflow
Correct
Incorrect
Correct answer
After approval of adjustment request
Correct
Incorrect
Correct answer
Question 135 of 137
Category: APCF – Solution introduction
Which methodology is at the core of the extension project controlling solution?
Question 136 of 137
Category: APCF – Progress and estimate data set
Link configuration options to their effect
Controls visibility of dataset columns
Skips manual dataset confirmation
Determines % complete logic
Creates new dataset periodically
Simplified progress and estimate column setup
Correct
Incorrect
Correct answer
Auto-confirm toggle
Correct
Incorrect
Correct answer
Progress calculation method
Correct
Incorrect
Correct answer
Scheduled dataset job
Correct
Incorrect
Correct answer
Question 137 of 137
Category: APCF – Earned value management
Which elements are required to calculate Estimate at Completion (EAC)?
Please select the two correct options to score the point